Riot Platforms stock jumps after $9.1B Anthropic AI deal revealed

Riot Platforms stock jumps after $9.1B Anthropic AI deal revealed
Vatsala Gaur
11 Aug 2026, 23:00 PM

powered by

Invezz
RIOT AI power contract

Buy Riot Platforms (RIOT). The $9.1B 20-year Anthropic deal plus the AMD agreement locks in long-duration demand for Rockdale capacity, turning Riot’s data-center buildout into a contracted, AI-infrastructure cash-flow story. The optional extensions raise upside to ~$16.1B, and management already guides meaningful annual NOI from the two contracts—this is a rerating catalyst beyond near-term crypto noise.

Key Risk: Anthropic delays or cancels the capacity ramp (deliveries start Dec 2027/Jun 2028), leaving Riot stuck with expensive build costs and underutilized power capacity.

Hut 8 AI infrastructure leverage

Buy Hut 8 (HUT). It’s already tied to the same Anthropic demand theme with a large AI data-center infrastructure program (initial ~$7B, up to ~$17.7B with options). If the market is paying for “Anthropic-backed megawatts,” HUT should benefit from the same sentiment and customer validation, even if the exact contract details differ.

Key Risk: Anthropic’s spending slows or shifts away from Hut 8’s planned phases, cutting contracted megawatts and impairing the expected value of renewals.

  • Riot Platforms' 20-yr deal with Anthropic to generate $9.1 billion revenue.
  • Optional five-year extensions could lift the contract value to $16.1 billion.
  • AI is becoming an increasingly important contributor to Riot's growth strategy.

Riot Platforms RIOT shares surged about 14% in premarket trading on Tuesday after a Bloomberg report identified Anthropic as the "leading frontier AI" company behind the Bitcoin miner's newly announced USD 9.1 billion (approx. $13.3 billion) infrastructure agreement.

Riot had disclosed on Monday that it secured a 20-year contract to provide 191 megawatts of computing capacity from its Rockdale, Texas campus, enough to power roughly 143,000 homes at any given time.

Bloomberg, citing people familiar with the matter, reported that Anthropic is the customer behind the deal.

The agreement runs through June 2048 and is expected to generate about USD 9.1 billion (approx. $13.3 billion) in revenue.

It also includes two optional five-year extensions, potentially lifting the total value of the contract to as much as USD 16.1 billion (approx. $23.5 billion).

AI pivot gathers pace

The Anthropic agreement marks another step in Riot's transformation from a cryptocurrency miner into an AI infrastructure provider.

Formerly known as Bioptix, a maker of diagnostic equipment for the biotechnology industry, Riot shifted its focus to Bitcoin mining years ago.

Now, like several crypto miners facing changing market dynamics, it is expanding into cloud computing and AI infrastructure.

The company has also signed a separate agreement with Advanced Micro Devices to build AI computing infrastructure.

Together, the Anthropic and AMD contracts cover 241 MW of contracted IT capacity at Rockdale.

Riot estimates the two agreements will generate about USD 520 million (approx. $757.8 million) in average annual revenue and between USD 416 million (approx. $606.2 million) and USD 462 million (approx. $673.3 million) in annual net operating income.

Riot expects to deliver the first 96 MW of capacity to Anthropic in December 2027, with the remaining capacity scheduled for June 2028.

To support the buildout, the company expects development costs of between USD 2.1 billion (approx. $3.1 billion) and USD 2.3 billion (approx. $3.4 billion), or roughly USD 11 million (approx. $16 million) to USD 12 million (approx. $17.5 million) per IT MW.

Bitcoin mining still matters, but AI is becoming central

Bitcoin mining remains Riot's largest business, but AI infrastructure is becoming an increasingly important contributor to its long-term growth strategy.

Second-quarter revenue rose 14% year over year to USD 174 million (approx. $253.6 million), beating analyst expectations of USD 152.1 million (approx. $221.6 million).

Bitcoin mining generated USD 113.7 million (approx. $165.7 million) in revenue during the quarter, while Riot's data center business contributed USD 23.2 million (approx. $33.8 million).

Its engineering segment added another USD 37.3 million (approx. $54.4 million).

The company mined 1,587 Bitcoin during the quarter, up from 1,426 a year earlier, although its average mining cost increased to $49,912 per Bitcoin.

Riot ended June with $548.9 million in cash and holdings of 11,380 Bitcoin.

Anthropic ramps up AI infrastructure partnerships

Anthropic has signed a series of infrastructure agreements in recent months to secure the computing power needed to support surging demand for its AI models.

The company recently struck a USD 10 billion (approx. $14.6 billion) deal with infrastructure startup Volta Infra Holdings and, in May, agreed to purchase nearly USD 45 billion (approx. $65.6 billion) worth of computing capacity from Elon Musk's xAI.

Last year, another bitcoin miner, Hut 8, announced a major artificial intelligence infrastructure partnership with Anthropic and cloud compute provider Fluidstack.

Under the agreement, Hut 8 will develop and deliver at least 245 megawatts of AI data centre infrastructure for Anthropic, with capacity potentially rising to as much as 2,295 megawatts across multiple phases.

The initial contract is valued at around USD 7 billion (approx. $10.2 billion), according to the company, with the overall value climbing to as much as USD 17.7 billion (approx. $25.8 billion) if all renewal options are exercised over the 15-year lease term.